YVR South Terminal Watermain Replacement Project
Client: Vancouver Airport Authority
Location: South Terminal, Vancouver Airport
Date Started: March, 2014
Date Ended: June, 2017
Wedler was retained by YVR to design and supervise the construction of new watermains in the South Terminal area of the airport. The works included 320 m of a new watermain adjacent the South Terminal, 110 m near the WestJet hangar, and 50 m near the Pacific Coastal Hangar. Some installations were completed below sea level which required significant de-watering. The project was completed in 2017.